What happens when I select the Spatial Fire Planning Proces on the Data Management tab?
When you select the SFP option on the Data Management tab, the following actions occur in the WFDSS application:
- FMU level Management Requirements are immediately disabled and can NEVER be re-enabled (they can be recreated but not re-enabled).
- All existing FMU shapes become Strategic Objective shapes.
- All Existing FMU codes become Strategic Objective codes.
- All Strategic Objective codes associated with existing shapes are activated while all other codes are deactivated. Note that active Strategic Objective text associated with deactivated Strategic Objective codes is deactivated.
- Administrative unit-wide Strategic Objectives and Management Requirements are unaffected.
- You can draw and upload Management Requirement shapes. (Strategic Objective shapes are managed nationally and will need to be submitted to a WFDSS Data Contact for upload.)